Home > A9 Dualling > Roadworks > A9 Dualling: Tomatin to Moy – Traffic management changes at Dalmagarry
Overnight traffic management on A9 Tomatin to Moy 13 April 2026

A9 Dualling: Tomatin to Moy – Traffic management changes at Dalmagarry

Road users are advised of upcoming changes to the road layout and traffic management on the A9 at Dalmagarry.

Overnight works – temporary signals and convoy system

For approximately three nights from Friday 17 April at 19:00 until Wednesday 22 April at 06:00, with no works taking place on the Saturday or Sunday evenings. Temporary traffic signals and a convoy system will be in place 250m south of the Ruthven road access junction.

  • Works will take place between 19:00 and 06:00
  • During these times, vehicles will be held at temporary traffic lights and guided through the works area by a convoy vehicle
  • The temporary traffic lights will be manned at all times
  • Delays are expected to be minimal

Temporary A9 realignment and new Ruthven road access

From Wednesday 22 April 2026, both lanes of the A9 will be temporarily realigned at Dalmagarry to support construction of a new bridge on the dual carriageway. As part of these works, the access junction from the A9 to Ruthven road will be repositioned.

A9 realignment layout

  • The temporary route will begin 250m south of the existing Ruthven road junction.
  • Traffic will move onto a temporary road west of the existing A9, before re-joining the main carriageway 250m south of the B9154 Moy South junction.
  • The new access to Ruthven road will be located approximately 100m south of the existing junction.

Using the new access

From Wednesday 22 April:

  • Road users can exit the A9 at the new Ruthven road access junction.
  • They will then travel 100m north on the existing A9 before turning onto Ruthven road as normal.

Clear signage will be in place throughout. This realignment and temporary access will be in place until early 2027.

An image showing the realignment and access route is provided below.

Please approach the area with care and allow extra time for your journey.

Access will be maintained at all times for emergency services, Ruthven road residents, pedestrians and cyclists.

All works are weather‑dependent and subject to change. Please check the Traffic Scotland website for any updates.